Line painting on County Road 49 to begin
Administrator | Nov 22, 2026 | Comments 0
UPDATE NOV. 20: Crews have completed paving on County Road 49 to approximately Bethesda Road. Paving will continue this weekend and throughout next week.
Line painting is scheduled to begin during the week of Nov. 23–27. Road markings will be painted along the entire length of County Road 49 before work pauses for the winter.
Second lift of asphalt placing begins on County Road 49
UPDATE Nov. 9 – 13 This past week, crews focused on gravel shoulder preparation, roadside ditching, and driveway culvert replacements along the corridor.
During the week of Nov. 9 – 13, the contractor is scheduled to begin placing the second lift of asphalt. Paving will start at the north end of County Road 49 and progress south as work advances.
Crews will also continue preparing the gravel shoulders for paving. Once complete, the second and third lifts of asphalt will create 2.0-metre (6.5-foot) paved shoulders along the corridor.
Full span layer of paving on County Road 49 this weekend
UPDATE OCT. 30: The major structural rehabilitation of County Road 49 reached another key milestone this week as the contractor completed rubblization of the existing concrete roadway.
The municipality’s report notes the contractor anticipates the first layer of asphalt, also known as the base lift, will be installed on the entire 17.2 km span of County Road 49 by the end of this weekend (Sunday, Nov. 1).
Next week, the contractor will focus on:
Full depth removals at crossroad intersections in order to blend to the new raised elevation of County Road 49
Work to prepare the existing gravel shoulders for asphalt.
Roadside ditching and some entrance culvert replacements
No paving is planned for Nov. 2 – 6.
Rubblization and base paving of County Road 49 continues
UPDATE Oct. 23: Rubblization of the existing concrete surface roadway continued past the Heidelberg Materials cement plant (1370 County Road 49) this past week.
Rubblization will continue next week. The municipality anticipates that rubblization will be complete within the next two weeks.
The first layer of base paving has been completed to just north of Bethesda Road.
Granular shouldering and the second layer of base paving is progressing southerly from the northern project limits.
Base paving is anticipated to continue throughout the entirety of next week.
Drivers can continue to expect delays of 5 to 10 minutes at both the rubblization and paving locations. Both lanes of traffic reopen at the end of each construction day. To help manage dust on gravel sections, the contractor is applying calcium and water as needed.
Base paving on County Road 49 continues
UPDATE OCT. 16: Rubblization of the existing concrete surface roadway continued south of Bethesda Road this past week and is to continue next week. The municipality anticipates that rubblization will progress past the Heidelberg Materials cement plant by the end of next week.
Base paving at the north end of the project is scheduled for Saturday, Oct. 17 and Sunday, Oct. 18. Base paving is to resume Wednesday, Oct. 21 and continue through Friday, Oct. 23.
Culvert and box culvert work and subdrain installations are now complete.
Drivers can continue to expect delays of 5 to 10 minutes at both the rubblization and paving locations. Both lanes of traffic reopen at the end of each construction day. To help manage dust on gravel sections, the contractor is applying calcium and water as needed.
County Road 49 paving has begun on north end
UPDATE OCT. 9: Paving began Friday, Oct. 9 at the north limit of the project at County Road 15 (Northport Road). Contractor, R.W. Tomlinson Ltd., plans to complete rubblization and the first two lifts of asphalt this construction season. The final surface lift is to be placed next year, as originally planned.
The rubblization process has advanced to Bethesda Road, representing more than nine kilometres of the 18-kilometre project corridor. The concrete (resonant frequency) breaker machine has returned to service after undergoing repairs earlier this week.
Culvert replacement work was completed this week. The installation of subdrain north of County Road 6 was also completed.
Work on this project will pause over the Thanksgiving long weekend. Crews are to be back on site on Tuesday, Oct. 13 to continue rubblization and paving operations. The contractor will also install subdrain south of County Road 6.
Drivers can continue to expect delays of 5 to 10 minutes through the construction zone. Both lanes of traffic reopen at the end of each construction day. To help manage dust on gravel sections, the contractor is applying calcium and water as needed.
Paving on part of County Road 49 soon
OCT. 2 UPDATE: As of Friday, Oct. 2, the rubblization process has advanced to just north of Bethesda Road, representing approximately nine kilometres of the 18-kilometre project corridor.
The contractor is currently planning to begin paving portions of the rehabilitated roadway on Thursday and Friday of next week.
All road cross-culvert replacement work has now been completed. Waterproofing work on existing concrete box culverts is ongoing and will continue as crews progress toward Picton.
New asphalt on the rubblized section of County Road 49 soon
SEPT. 25: The municipality’s County Road 49 rehabilitation report: Sept. 28 – Oct. 2:
Tomlinson has rubblized and placed gravel on approximately 6.5 km of County Road 49 as of Friday, Sept. 25. Crews began work at County Road 15 (Northport Road) and have progressed to approximately Lyons Road.
Construction work on County Road 49 is continuing seven days a week from 7 am to 7 pm. The municipality agreed to allow the contractor to work on weekends to make sure the planned road work is completed this year.
Drivers can expect delays of between 5 to 10 minutes. Both lanes of traffic will re-open at the end each construction day. The contractor is applying calcium and water to the gravel sections to suppress dust.
Rubblization is a road rehabilitation technique that involves breaking the existing concrete road into small pieces and leaving them in place, creating a strong foundation for the new asphalt road.
The contractor tentatively plans to place new asphalt on the rubblized section of County Road 49 beginning the week of Oct. 5.
Culvert replacement and waterproofing update
Replacement of culverts is to be completed by the end of this week.
Waterproofing of existing concrete box culverts will continue to progress towards Picton.
During the culvert work, there will be single-lane closures in the vicinity of the work from 7 am – 7 pm. Temporary traffic signals are to help maintain the flow of traffic and minimize delays.
The municipality reminds drivers that a temporary 60 km/h speed limit is in effect throughout the construction zone.
The municipality continues to monitor and maintain areas where the concrete has been cut out and removed for the cross-culvert replacement. “Bump ahead” signs are installed near the road cuts.
Traffic update
With a 5- to 10-minute wait expected during the major rehabilitation work, using the alternate route instead of staying on County Road 49 may provide little to no advantage for commuters.
However, the municipality recognizes that some drivers may use or continue to use County Roads 5 and 15 as an alternate.
What residents can expect during construction
A machine breaking the existing concrete into rubble.
Rollers compacting the roadway.
Trucks and paving crews placing new asphalt.
Unpleasant odors from the asphalt that could last up to several hours.
A smoother road surface once construction is complete.

– Dale Miller photo
County Road 49 construction now seven days a week
SEPT: 18 Construction work on County Road 49 will now also occur on weekends to help make sure palnned work is completed this year.
The municipality reports the additional workdays will help the contractor finish breaking up the existing road and paving the first two layers of asphalt before the construction season ends. The contractor is to install the third and final layer of asphalt in 2027 as originally planned.
The project contractor experienced delays securing the specialized equipment due to work visa issues. Work to break up the existing concrete road into granular material began on Sept. 8, about a month later than originally planned.
The County thanks residents, businesses, and motorists for continued patience and cooperation as the infrastructure improvement project moves forward.
County Road 49 to be ready to rubble Tuesday
SEPT. 6: “Rubblization” of County Road 49 is scheduled to begin on Tuesday, Sept. 8 now that the specialized equipment has arrived from the United States.
This work was slated to get underway earlier this summer; however, work visa issues impacted the contractor’s ability to bring both the specialized equipment and operating crew into Canada.
Rubblization is a road rehabilitation technique that involves breaking the existing concrete road into small pieces and leaving them in place, creating a strong foundation for the new asphalt road.
The municipality, in an update, reports:
Crews are to start at County Road 15 (Northport Road) and work their way south. Crews will be on site Monday – Friday, 7 a.m. to 7 p.m.
The contractor intends to rehabilitate County Road 49 in sections approximately 1- 2 kilometres in length:
A minimum of one lane of traffic, operating under alternating directions, is to be maintained at all times.
The rubblizing machine will break up the concrete in one lane for approximately 1 – 2 kilometres.
Crews will come behind to compact and level out the road, followed by a layer of new granular material.
When that lane of road is complete, crews will turn and work back in the other direction and repeat the process on the adjacent lane. Once both lanes have been rubblized and a new layer of granular material has been placed, the base lift of asphalt will be placed over both lanes.
Drivers can expect delays of between 5 to 10 minutes. Both lanes of traffic will re-open at the end each construction day and on weekends. Calcium chloride will be applied to the gravel sections of the road to suppress the dust.
What residents can expect during construction
Residents and drivers might notice:
A machine breaking the existing concrete into rubble.
Rollers compacting the roadway.
Trucks and paving crews placing new asphalt.
Unpleasant odors from the asphalt that could last up to several hours.
A smoother road surface once construction is complete.
Culvert replacement work continues Replacement of culverts and waterproofing of existing concrete box culverts will continue to progress toward Picton.
During the culvert work, there will be single-lane closures in the vicinity of the work from 7 a.m. – 7 p.m. Temporary traffic signals will help maintain the flow of traffic and minimize delays.
The municipality reminds drivers that a temporary 60 km/h speed limit is in effect throughout the construction zone. Please follow posted signage and reduce your speed when approaching road cuts.
The municipality continues to monitor and maintain areas where the concrete has been cut out and removed for the cross-culvert replacement. “Bump ahead” signs are installed near the road cuts.
Traffic update
With a 5- to 10-minute wait expected during the major rehabilitation work, using the alternate route instead of staying on County Road 49 may provide little to no advantage for commuters.
However, the municipality recognizes that some drivers may use or continue to use County Roads 5 and 15 as an alternate. Staff have notified the OPP about the possibility of increased traffic on these roads, and the local police have agreed to provide additional traffic law enforcement during rehabilitation.
County Road 49 rubblization delayed due to visa issues
UPDATE AUG 11: Rubblization of County Road 49 has been delayed. Work visa issues have impacted the contractor’s ability to bring both the specialized equipment and operating crew into Canada.
Despite the schedule change, the municipality states its contractor, R.W. Tomlinson Ltd., still plans to complete rubblization and the first two lifts of asphalt this construction season. The final surface lift is to be placed next year, as originally planned.
The municipality’s report today note culvert replacement operations, which began at the Bay of Quinte Skyway Bridge, have now advanced south of Bethesda Road.
Once the culvert replacement work is complete, the contractor will begin excavating and waterproofing the existing concrete box culverts to extend their service life.
The municipality continues to monitor and maintain areas where the concrete has been cut out and removed for the cross-culvert replacement. “Bump ahead” signs are installed near the road cuts.
A temporary 60 km/h speed limit is in effect throughout the construction zone. Follow posted signage and reduce speed when approaching road cuts.
County residents and visitors have endured decades of rough rides down County Road 49 and spent years asking the County and upper levels of government to “just fix the road!”
Finally work is under way – but the process will require more patience.
“I get it: no one likes to sit in traffic, especially in the summer. You have places to go and people to see. However, with some small sacrifices from drivers, we are going to end up with a massive gain for Prince Edward County,” said Mayor Ferguson.
The County’s contractor, R.W. Tomlinson Ltd., is first replacing culverts and single lane closures will continue.
The specialized machine that will “rubblize” the road is tentatively scheduled to arrive in the County on Aug. 9 with work to begin the next day.
Rubblization is a road rehabilitation technique which involves breaking the existing concrete road into small pieces and leaving them in place, creating a strong foundation for the new asphalt road.
Crews plan to start at County Road 15 (Northport Road) and work their way south. A minimum of one lane of traffic, operating under alternating directions, is to be maintained at all times throughout construction.
Drivers can expect delays of between five to 10 minutes as the contractor works to rehabilitate two kilometres of road at a time.
The municipality notes staff explored breaking the project into smaller sections to shorten wait times but learned drivers would only save a little time, while the project would take longer, and could prevent the entire 18.6 km road from receiving new asphalt in 2026.
“We know it’s an aggressive timeline, but we owe it to the people of Prince Edward County to get as much of the road done as possible during this construction season. Like everyone else, I am tired of dodging potholes on County Road 49. Let’s make them disappear in 2026,” added Ferguson.
In March, 2026, the Province of Ontario announced funding of up to $44,500,000 for the rehabilitation project. This funding includes a municipal contribution of $7,805,700 for the 1.1 km urban section of the Picton Main Street Phase 3 project.
Council awarded the tender in May for $18,679,000 plus applicable taxes.
Opened in 1966, County Road 49 spans 18.4 kilometres, of which 17.3 kilometres is concrete pavement. The road connects Picton with the Bay of Quinte Skyway Bridge, one of the largest entry-points into the municipality from Highway 401. County Road 49 consistently ranks as one of the worst roads in Ontario by the Canadian Automobile Association.
Filed Under: Featured Articles • Local News